PMP Exam Questions: 5 Sample Questions with Answers and Tips (2026 Exam)

If you are preparing for the PMP® certification, the fastest way to find out whether you are ready is to practise with realistic PMP exam questions. The PMP exam does not test whether you can memorise definitions. It tests whether you can choose the best action in a real project situation, the way PMI® expects a project manager to think.

In this guide we explain what the PMP exam questions look like since the exam was updated on 9 July 2026, walk through five sample questions with explanations, and share practical tips from our PMP classes in Malaysia.

Participants of a PM Advance PMP exam preparation class in Bandar Baru Bangi holding their certificates of completion

What the PMP exam looks like in 2026

  • Number of questions: 180, including a small number of unscored pretest questions. You will not know which ones are unscored.
  • Time: 240 minutes, with two optional breaks.
  • Domains: People (33%), Process (41%) and Business Environment (26%). Business Environment has grown a lot compared with the previous exam, so expect more questions on value, strategy, compliance and organisational change.
  • Approaches: questions cover predictive (waterfall), agile and hybrid projects.

For the official details, see the PMP certification page on PMI.org. For a full breakdown of what changed, read our article on PMP exam changes 2026.

Types of PMP exam questions

  • Multiple choice: one correct answer out of four. Most questions are this type.
  • Multiple response: choose two or more correct answers. The question tells you how many to select.
  • Matching and drag-and-drop: match terms, steps or artefacts to the right description or order.
  • Hotspot (point-and-click): click the right area of a chart or diagram, such as a burndown chart or a schedule.
  • Scenario-based questions: almost every question describes a situation and asks what the project manager should do next or first.

5 sample PMP exam questions with answers

Try to answer each question before reading the explanation.

Question 1 (People)

Two senior engineers in your team keep arguing in meetings about the technical design, and other team members have stopped sharing ideas. What should the project manager do first?

  1. Escalate the conflict to the functional manager.
  2. Meet the two engineers privately to understand the root cause of the disagreement.
  3. Make the design decision yourself to stop the argument.
  4. Remove one of the engineers from the project.

Answer: B. PMI expects the project manager to address conflict directly and early, starting by understanding the cause, usually in private. Escalating, forcing a decision or removing people are not the first step.

Question 2 (Process)

Halfway through a predictive project, a key stakeholder asks the project manager to add a new report to the system. What should the project manager do first?

  1. Ask the team to start building the report so the stakeholder stays satisfied.
  2. Reject the request because the scope baseline is already approved.
  3. Assess the impact of the request on scope, schedule, cost and risk.
  4. Submit the request directly to the change control board.

Answer: C. In a predictive project, every change request goes through integrated change control. The project manager first analyses the impact, then submits the change request with that analysis for a decision. Doing the work without approval leads to scope creep.

Question 3 (Agile)

During a sprint, the product owner wants to add a high-priority user story. The team has already committed to the sprint goal. What is the best response?

  1. Add the story to the current sprint and ask the team to work overtime.
  2. Add the story to the product backlog and prioritise it for the next sprint planning.
  3. Cancel the sprint immediately.
  4. Ask the sponsor to decide.

Answer: B. The product owner manages the product backlog. New work is normally prioritised in the backlog and pulled into a future sprint, so the team can protect the current sprint goal. Overtime and cancelling the sprint are not the default agile response.

Question 4 (Business Environment)

A new government regulation will affect one of your project’s deliverables in six months. What should the project manager do?

  1. Ignore it until the regulation takes effect.
  2. Evaluate the impact of the regulation on the project and update the plans and risk register accordingly.
  3. Ask the legal department to handle it.
  4. Stop work on the deliverable until the regulation is finalised.

Answer: B. Compliance is part of the project manager’s job. The PMP exam expects you to assess external changes proactively, involve the right experts and adjust the project, rather than wait or hand it off completely.

Question 5 (Process, risk)

A risk identified during planning has now occurred. The planned response is in the risk register. What should the project manager do?

  1. Implement the agreed risk response and inform the risk owner.
  2. Hold a meeting to identify new risks.
  3. Use the management reserve immediately.
  4. Escalate the issue to the sponsor.

Answer: A. When a planned risk occurs, you implement the planned response (with the risk owner) and record it in the issue log. Escalation and reserves come into play only if the response is not enough or the impact is outside your authority.

How to answer PMP exam questions: 7 practical tips

  1. Read the last sentence first. Check whether the question asks what to do first, next, or what should have been done.
  2. Identify the approach. Decide whether the scenario is predictive, agile or hybrid. The best answer often depends on it.
  3. Think like PMI, not like your company. Choose the answer that follows good practice, even if your organisation does it differently.
  4. Prefer proactive, collaborative actions. Analyse, talk to people and solve problems before escalating.
  5. Eliminate extreme answers. Options like “fire”, “ignore” or “cancel” are rarely correct.
  6. Manage your time. 180 questions in 240 minutes is about 80 seconds per question. Mark difficult ones for review and move on.
  7. Practise full mock exams. Sit at least two full-length timed mock exams before the real one to build stamina.

Where to practise PMP exam questions

Use practice questions that match the 2026 exam content outline. Older question banks written for the previous exam do not cover the new Business Environment weighting well. Always read the explanation for every question, including the ones you got right, so you understand the reasoning PMI expects.

If you are still deciding which certification suits you, read PMP vs CAPM, and for the full cost picture see how much PMP certification costs in Malaysia.

Prepare for the PMP exam with PM Advance

Our 5-day PMP exam preparation course gives you the project management education hours PMI requires to apply for the exam, scenario-based practice questions aligned with the 2026 exam, and guidance from PMP-certified trainers. PM Advance is a PMI Authorized Training Partner (#4930), and the course is HRD Corp claimable for eligible Malaysian employers.

Contact us to check the next intake dates or to arrange in-house training for your team.